Hey Pawan so I’ve started with this and began building the custom script. I want the total value coming from the delivery notice of a sale of ‘Support Hours’ to the project customer and then to have it subtracted from that total when a time sheet is submitted against it.
Would a get_value be too basic for this? How do I isolate Project based delivery notices?
that is very interesting for us also, but for our case i need to have this inside a task.
A Project are tasks - and they can have different activity types, and for every task, i plan to have some hours. For example 10.
And if there is a timesheet, where logged 2 hours, i can see, that i have a rest of 2 hours.
Very good also to know, the planned hours for all tasks inside the project - and the rest of hours, if some are logged in a timesheet.
Who can help me or share the custom-script?
Thanks