Budget Variance Report- department instead of CC

Hello,
My budget was prepared department wise, in the Budget Variance Report only the choice between CC and Project.

How could I choose the department?

V13

Regards
Ahmad

Have you seen Accounting Dimensions? That’s probably what you’re looking for.

https://docs.erpnext.com/docs/v13/user/manual/en/accounts/accounting-dimensions

Screen Shot 2021-08-22 at 2.31.22 PM

Hi,
As you can see only project of cost centre, How could I choose department?

Screen Shot 2021-08-22 at 2.35.51 PM

I already have a department in the accounting dimensions

You’re right. There’s a bug in this line of code:

It’s supposed to be adding other dimensions to the dropdown list, but erpnext.dimension_filters doesn’t seem to refer to anything anymore.

Thank you

Make your departments also cost centers

Thanks for your comment.
Of course, we can but better to use the accounting dimension.

Regards