Hello everyone from Accra Ghana!
I’ve created a production order for item X for 250,000 pieces. I’ve done transfer of raw materials just fine. The system generated raw material stock entry for the production that works fine. However, not ALL of product X has been manufactured yet. Only 27500 has been transferred from the production floor to the warehouse.
Now I want to replicate this in the system. However it’s not working. When I hit update FG on the production order, the stock entry the system generated requires that I transfer all of the 250,000, otherwise I get an error that says
Quantity in row 2 (27500.0) must be same as manufactured quantity 250000
Did not save
It is important to note it is only the system generated finished goods transfer from production order that has the valuation cost for the finished goods. If I make a manual stock entry to transfer the 27500, I don’t know what cost to use, how much raw material/has been consumed yet etc.
Essentially, the system shouldn’t mandate that the stock entry generated from the transfer finished goods button on the production order necessarily transfer all the finished goods. I’m stuck in a case where I can’t transfer part of the manufactured goods from the production floor because using stock entry requires I manually compute the valuation of finished goods, how much raw materials is consumed at this point and so on.
So how I do partial finished goods transfer from production and have a system generated valuation rate for the finished goods and updated valuation in work in progress as well?