The company is manufacturing bearings.
They got an order from their customer in which they have to use the raw material provided by their customer.
In such situation how to enter Raw Material received entry in ERPNext and will it have any effect on Accounting?
Regards,
1 Like
pss
2
Good Question. Please see the attached page. I think this will answer your question.
https://docs.erpnext.com/docs/v13/user/manual/en/manufacturing/articles/customer-provided-items
It would be nice to know the impact on accounting when you try it out.
1 Like
Thank you for the link.
After reading the document it seems I will have to create two Items.
- which is purchased
- which is supplied by customer
Are my assumptions right?
Regards,