How to produce more or less than planned qty?

It doesn’t seem possible to produce more or less than the planned qty on the Work Order.

What kind of ultra super precise shop use this manufacturing module lol

For real world use case, anyone came up with a solution to this ?

1 Like

Try changing the variantion % in Manufacturing Settings. That should allow you to overproduce compared to the planned quantity.

As for underproducing, you should be able to short close the Work Order and then backflush additional quantities that were used.

Great, thanks for pointing out the overproduction settings.

As for underproducing, what does it mean short close ?

I know you can change status to Stopped, but I want it to be Completed.

Is there a way to under produce in job card as well, our employee don’t know in advance the quantity they will produce and we want to time them in job card to calculate operation cost.

We modified erpnext source code within our own fork to remove all those nonsense validations