I want to calculate COST, Quantity wise instead of Per Hour basis in a workstation.
I Just want to make a work order in which cost should be calculate for example
cost = rate x quantity
I want to calculate COST, Quantity wise instead of Per Hour basis in a workstation.
I Just want to make a work order in which cost should be calculate for example
cost = rate x quantity
Hi,
You can always consume the consumables in Material Consumption for Manufacture.
Thanks,
Divyesh Mangroliya
Thanks for your kind reply,
whenever i try to make work order consumable cost is fixed with hour, i want to fixed it with quantity. how can I change the type of consumable cost.
Hi,
You can consume the consumable quantity as part of material input as and when required in the work order.