Hi everyone,
I’m using ERPNext’s MRP (Material Requirements Planning) module and I have a few questions regarding its functionality:
- Does MRP consider lead times when generating material requirements?
- Specifically, does it take into account the lead time for each item to ensure that the required materials are available on time?
- Can MRP handle long-term planning?
- For example, can it generate a plan for 1 month or 3 months ahead, providing weekly demand and procurement plans, as well as arrival schedules?
Any insights or guidance would be greatly appreciated.
Thanks in advance
NCP
2
I think, you have to check this.
naikun
3
Thanks for your reply.
I read the link. I want to know if are there some demos or training for erpnext mrp?
For exapmle, can ERPNext implement the following scenario? and how?
Example Scenario
Assume we are a small electronics manufacturer producing a product called “SmartGadget.” This product consists of the following components:
- SmartGadget (Finished Product)
- Display
- Battery
- Chipset
- Enclosure
Bill of Materials (BOM)
Product/Component |
Unit |
Quantity |
Cost |
SmartGadget |
Each |
- |
- |
|
Display |
1 |
$10 |
|
Battery |
1 |
$5 |
|
Chipset |
1 |
$15 |
|
Enclosure |
1 |
$3 |
Material Requirements Planning (MRP)
Product/Component |
Demand Quantity |
Demand Date |
Lead Time |
Planned Receipt Date |
Planned Order Release Date |
Cost |
SmartGadget |
100 |
Day 5 |
3 days |
Day 2 |
Day 2 |
$3300 |
Display |
100 |
Day 2 |
2 days |
Day 0 |
Day 0 |
$1000 |
Battery |
100 |
Day 2 |
1 day |
Day 1 |
Day 1 |
$500 |
Chipset |
100 |
Day 2 |
3 days |
Day -1 |
Day -1 |
$1500 |
Enclosure |
100 |
Day 2 |
1 day |
Day 1 |
Day 1 |
$300 |
Production Schedule
Product/Component |
Production Quantity |
Start Date |
Completion Date |
Work Center |
Daily Capacity |
Required Hours |
Hourly Cost |
SmartGadget |
100 |
Day 2 |
Day 5 |
WC1 |
50 units/day |
3 days |
$600 |
Display |
100 |
Day 0 |
Day 2 |
WC2 |
50 units/day |
2 days |
$400 |
Battery |
100 |
Day 1 |
Day 2 |
WC3 |
100 units/day |
1 day |
$200 |
Chipset |
100 |
Day -1 |
Day 2 |
WC4 |
50 units/day |
3 days |
$600 |
Enclosure |
100 |
Day 1 |
Day 2 |
WC5 |
100 units/day |
1 day |
$200 |
Cost Accounting
Product/Component |
Total Cost |
Unit Cost |
SmartGadget |
$3900 |
$39 |
Display |
$1000 |
$10 |
Battery |
$500 |
$5 |
Chipset |
$1500 |
$15 |
Enclosure |
$300 |
$3 |