Production Plan- Multiple BOM selection for material planning

Hi ,

When we do production plan, if an item A is used in two different projects such as

Project A : Item A :100
Project B : Item A : 50

Question is , how to perform production plan keeping 2 Bill of Materials at a time ? since Item A is common for both the projects.

by the way right now am using blank option as shown below

image

Please do suggest

Hi,

Create a Material Request from Project A and Project B as per their requirement and in Production Plan select the “Material Request” option instead of Blank.

Thanks,

thanks for your response.

let me check and revert. @mangroliya