Production Plan Qty Issue

I have qty in hand un check ignore available stock but still required qty is not calculating correctly for e.g my plan qty is this item is CARTONS-29X39.5X32-CM-5 PLY is
qty as per bom : 2500
plan to requested : 2480 (qty as per bom - projected qty)
qty in stock : 170 not effecting and material request created of qty 2480 why ?

Hello,

We are facing a similar challenge where the quantity that is low in stock VS the required quantity as per BOM is showing a calculation error.
Were you able to figure a solution yet?

Our issue =
If my required quantity as per BOM is 3000 unit and I have only 250 units in stock, then ideally it should show 2750 units under Plan to Request Qty.
But its showing a wrong number.
When I further checked the issue, what its doing is - ERPNExt is fetching Projected Qty from somewhere and then deducting this from the Total Required Qty as per BOM.
The result is - Our team is not able to figure the correct ‘Deficit’ material to order.
Can you help please. thanks

@Mohtashim_Shoaib Pls check This checkbox and then Get Raw material again.

I found out one solution that go to bin and recalculate the bin qty, for my case my issue is resolved.