Project task premissions

In erpnext is it possible to have some tasks visible to some users and invisible to others in the same project?

Hi,

There are two approaches:

  1. Don’t give permission on Project and share the tasks with concerned users which you want them to see them and act on it.

  2. You can set the permission allow permission for each task which you want to show them in User Permission. With these users can only access the task for which they have permission. The drawback is whenever someone adds new tasks, and you want to show this task to some users, you need to set the permission for it every time.

Thanks,

Divyesh Mangroliya

1 Like