Update BOM Cost

Hi,

I have a scenario just want to know the outcome of that.
I have created a BOM of item X where Y, Z are Sub-Assemblies and Y1, Y2 and Z1,Z2 are respectively the components of Sub-Assembly Y and Z.
Now there is no rate defined in the system against these items.
Now if I purchase Y1,Y2,Z1,Z2 then will the system update the cost of BOM or we have to manually update the cost of BOM by pressing “Update BOM Cost” button in BOM.

Hi,
In version -5,

  • you can use “Update Cost” button
    -When you submit BOM and "Click on "Update Cost"button then ’ Amount’
    get calculated.
    -‘Rate’ will be displayed in “BOM”,which was given at the time of submitting “Purchase Receipt”.

Shraddha Ranjane
New Indictrans Technologies Pvt. Ltd.