Capacity Planning: incorrect total time in job time Log

Hey all,

I want to use capacity planning and I have defined a time for each operation in each BOM.

For 1 piece the production time is set to 10 mins. Therefore the total production time for 10 pieces should be 100 mins. But in the Job Card only 30 min are suggested/planned.

Does anyone know this problem? Is it an error or a setting?

I think the same problem is described here.

Thanks for any help.
Greetings Lukas

Here are the manufacturing settings.

Can no one here say anything about this?